單項(xiàng)選擇題

A switch that is to be added to the production network has been preconfigured (trunks, VLANs, VTP, and STP) and was tested in your lab. After installing the switch into the network, the entire network went down. 
What might explain what happened? ()

A.The new switch happened to be running Cisco Catalyst operating system, while the other network switches were running Cisco IOS Software.
B.The configuration revision of the new switch was higher than the configuration revision of the production VTP domain.
C.The link costs on the new switch are set to a high value, causing all ports on the new switch to go into a forwarding mode and none into blocking mode, thereby causing a spanning-tree loop.
D.The ports connecting to the two switches have been configured incorrectly. One side has the command switchport mode access and the other switchport mode trunk.


您可能感興趣的試卷

你可能感興趣的試題

1.單項(xiàng)選擇題

You have just created a new VLAN on your network for inter-VLAN routing.  
What is one step that you should include in your VLAN-based implementation and verification plan?()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the proper IP address space assigned to it for the new VLAN. 
D.Verify that the VLAN virtual interface has been correctly created and enabled.

2.單項(xiàng)選擇題

You have just created a new VLAN on your network for inter-VLAN routing. 
What is one step that you should include in your VLAN-based implementation and verification plan?()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the proper IP address space assigned to it for the new VLAN. 
D.Verify that the VLAN virtual interface has been correctly created and enabled.

3.單項(xiàng)選擇題

You have just created a new VLAN on your network.
 What is one step that you should include in your VLAN-based implementation and verification plan? ()

A.Verify that trunked links are configured to allow the VLAN traffic.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.
D.Verify that different native VLANs exist between two switches for security purposes.

4.單項(xiàng)選擇題

You have just created a new VLAN on your network.
 What is one step that  you should include in your VLAN based implementation and verification plan? ()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the VLAN was added on all switches with the use of the show vlan command. 
C.Verify that the switch is configured to allow for trunking on the switch ports.
D.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.

5.單項(xiàng)選擇題What is a critical piece of information that you should have when creating a VLAN-based implementation plan?()

A.approval from senior management
B.end-user requirements
C.IEEE 802.1X authentication parameters
D.a summary implementation plan

6.單項(xiàng)選擇題When you create a network implementation VLAN solution, what is one procedure that you should include in your plan?()

A.Perform an incremental implementation of components.
B.Following the PPDIOO model, implement the entire solution and then test end-to-end to make sure that it is performing as designed.
C.Implement trunking of all VLANs to ensure that traffic is crossing the network as needed before performing any pruning of VLANs.
D.Test the solution on a segmented portion of a lab network prior to rolling out across the entire network.

7.單項(xiàng)選擇題

You are planning a new VLAN-based network solution. 
What is one item you should consider when creating your implementation plan as it concerns VLANs?()

A.generic router and switch configuration parameters
B.end-to-end test plan after all components have been installed and  configured
C.administrator assignments
D.rollback plan

8.單項(xiàng)選擇題What network information do you need when you plan to implement a VLAN-based solution?()

A.default VLAN information for all unused switch ports
B.802.1x configuration parameters 
C.number of IP subnets needed
D.IP routing protocol information

10.單項(xiàng)選擇題Which Cisco IOS command globally enables port-based authentication on a switch? ()

A.aaa port-auth enable
B.radius port-control enable
C.dot1x system-auth-control
D.switchport aaa-control enable

最新試題

Which two statements are true when the extended system ID feature is enabled? ()

題型:多項(xiàng)選擇題

Which two statements about the various implementations of STP are true?()

題型:多項(xiàng)選擇題

What must be the same to make multiple switches part of the same Multiple Spanning Tree (MST)?()

題型:單項(xiàng)選擇題

What will occur when a nonedge switch port that is configured for Rapid Spanning Tree does not receive a BPDU from its neighbor for three consecutive hello time intervals?()

題型:單項(xiàng)選擇題

Which option correctly identifies the Cisco IOS switching methods in descending order from the fastest method to the slowest method?()

題型:單項(xiàng)選擇題

Based on the show spanning-tree vlan 200 output shown in the exhibit, which two statements about the STP process for VLAN 200 are true? ()

題型:多項(xiàng)選擇題

Refer to the exhibit. What will happen when one more user is connected to interface FastEthernet 5/1? ()

題型:單項(xiàng)選擇題

Which three statements are true of the Link Aggregation Control Protocol (LACP)?()

題型:多項(xiàng)選擇題

Refer to the exhibit. For what purpose is the command show ip cef used?()

題型:單項(xiàng)選擇題

Refer to the exhibit. LACP has been configured on Switch1 as shown. Which is the correct command set to configure LACP on Switch2?()

題型:單項(xiàng)選擇題